The Nanakuli turn lane is still on schedule to be completed by the end of the year. Here is a project status update:
Route 93 — FARRINGTON HIGHWAY INTERSECTION IMPROVEMENTS AT NANAKULI AVENUE & HALEAKALA AVENUE
Progress/Schedule
Construction Phase
NTP Date: 11/10/14
Percent Complete: 56%
Cost: $ 13.6 Mil
Scope
THE SCOPE OF WORK FOR THE SUBJECT PROJECT INCLUDES INSTALLING AUXILIARY LEFT-TURN LANES FROM FARRINGTON HIGHWAY INTO HALEAKALA AVENUE AND NANAKULI AVENUE; INSTALLING SIDEWALKS; AND RELOCATING UTILITIES, TRAFFIC SIGNALS, RAILROAD TRACKS, A BIKE LANE AND HIGHWAY LIGHTING.
Other Information
Project Number: STP-093-1(22)
Starting Milepost: 4.85
Ending Milepost: 5.64
Point of Contact: SAMUEL ROMBAOA
Email: Samuel.P.Rombaoa@hawaii.gov
Here is information regarding a link to learn about other HDOT projects:
On Jul 20, 2017, at 3:47 PM, Sniffen, Edwin H <edwin.h.sniffen@hawaii.gov> wrote:
Aloha Senators and Representatives:
DOT Highways has recently included project status data on the DOT Website. This data includes all projects to be delivered into construction in the next 2 years. The data is open to the public and is accessible at the following link:
http://histategis.maps.arcgis.com/apps/MapSeries/index.html?appid=f69cd64b5d9a43b08ad6620d07b5e4c4
or through the DOT website, hit home tab, Highways, Major Projects, and Project Map.
A map showing lines on our transportation system will allow the viewer to locate projects along the federal highway system. Alternatively, the viewer can click on the “View a PDF list of Projects by Area” tab located on the right side of the screen. This will allow the viewer to view all projects in a list format.
This is our first roll out of the information, and we will continue to add content to the page. If you would like information on a project you don’t see, have questions about the site, or have suggestions to make it better please feel free to email me.
Mahalo,
Ed